Autumn Renovations 2017:


Below is a list of work done on Llanbradach's Bowling Green for their Autumn renovations.


1. Verticut out the moss & cut Solid tine to 100mm depth.
2. Applied 100kg of Calcium.
3. Applied 100kg of Symbio Traceolite.
4. Rubber crumb applied to heads to aid compaction & wear/tear.

5. Seeded and dressed bare areas & heads.
6. Double sorrel roll.
7. Overseeded with a premium fescue bent mix.
8. Materials dragged matted into tine holes.